How to compare quotes for robot components
Request the same revision, quantity and delivery point from each supplier. A lower unit price can still produce a higher first-batch total.
Compare two supplier quotes
Compare the same configuration, currency and delivery point. Leave unconfirmed charges blank; enter 0 only for a confirmed zero charge. This tool provides no market prices and submits no purchase.
Changing currency changes formatting only, with no FX conversion. Enter a per-unit price and batch totals for the other charges.
| Quote item | Supplier A | Supplier B |
|---|---|---|
| Minimum order (units) | ||
| Unit priceUSD | ||
| Tooling / setupUSD | ||
| TestingUSD | ||
| FreightUSD | ||
| Tax and dutiesUSD | ||
| Parts + tooling + testing | ||
| Total to delivery point |
Send one RFQ to every supplier
Specify the drawing revision, interfaces, sample and production quantities, acceptance test and required arrival date. Ask each supplier to identify substitutions and exclusions.
Put the costs in separate columns
For each quantity tier, record currency, minimum order, unit price, tooling, testing, freight, taxes, delivery point, payment terms and quote expiry. Label missing amounts “unconfirmed” so they are never counted as zero.
Calculate the first-batch total
Illustrative example: 20 units at $180 plus $600 tooling cost $4,200. At $205 per unit with tooling included, the same batch costs $4,100. Both totals exclude freight and tax. Confirm tooling ownership and whether the fee recurs before comparing repeat orders.
Attach a test and a date
For a joint actuator, compare continuous torque at the same speed, duty cycle and cooling conditions. Mark supplier claims separately from sample results. Ask what starts the lead-time clock: deposit, drawing approval or sample acceptance.